Hello,
I started custom below work flow but its status remains "Active" because process is stucked at the activity node. When i edit running work flow and manually change activity node's state to complete, work flow is successfully completed.
What do i need to do for automatically switch activity node's state to complete? By the way when we use email node instead of activity node, it is not stucked but we must use Activity Node in order to create task for related users.
Thanks in advance.
so in that task you need to have them complete it otherwise that task stays open en therefor also the WF