Decision node selecting wrong fulfilment workflow in RSA Governance & Lifecycle
Article Number
Applies To
- RSA Identity Governance & Lifecycle 7.5.2 GA
- RSA Identity Governance & Lifecycle 7.5.0 GA
- RSA Identity Governance & Lifecycle 7.2.1 P04
- RSA Identity Governance & Lifecycle 7.2.0 P08
Issue
If a decision node is used to select between two fulfillment phase nodes the workflow incorrectly chooses both fulfilment phase nodes. Customers may report this simply as the wrong fulfillment process being used.
Cause
Resolution
This issue is resolved in the following versions
- RSA Identity Governance & Lifecycle 7.5.2 P04
- RSA Identity Governance & Lifecycle 7.5.0 P08
- RSA Identity Governance & Lifecycle 7.2.1 P12
Workaround
Related Articles
Selecting the Web Express Approver Inbox fails with 500 Internal Server Error 6Number of Views RSA Certificate Manager installation fails with error "XrcNOTFOUND: unable to locate requested member or object" when sele… 13Number of Views For secondary remediator, Maintain All doesn't work after selecting Clear All option 3Number of Views Enable Enrollment by Selecting Identity Sources 40Number of Views Form control type 'Drop Down Select with Web Service' displays Unauthorized error in RSA Identity Governance & Lifecycle 7… 143Number of Views
Trending Articles
RSA Authentication Manager 8.9 Setup and Configuration Guide How to 'Trust' the RSA Authentication Manager Security Console Self-Signed Root CA certificate and prevent Cert warnings. RSA Authentication Manager 8.9 Release Notes (January 2026) Configure RSA Authentication Manager as a Secure Proxy Server for Cloud Access Service RSA Authentication Manager Upgrade Process
Don't see what you're looking for?