Hello guys,

based on "Attribute change" rules, I assign local entitlements (LE) to the
user to trigger specific workflow and provisioning commands for Active
Directory accounts.

I have two main types of LE:

* LEs, that move an account (this is used to move an account to different OU, based on user attribute)
* LE, that update an account attributes (this is used to update attributes like title or department in AD, when user's title or department is changed in HR system)

And attribute change rules:

* When user attribute value is changed to one of {a, b, c}, add "Move account" LE to specific OU
* When user attribute value is changed to one of {d,e,f}, add "Move account" LE to different specific OU
* When user attributes values are changed to any value (this attributes is different from the ones above), add "Update an account" LE.

The problem is when multiple LEs are assigned to the user, because multiple
rules are triggers.

For example, after identity collection ran, two LEs are assigned to the user
and two change requests are created:

* Move an account to different OU
* Update an acccount

These two change requests are run simultaneously and the problem occurs when
account is moved to different OU. G&L does not have the new info about this
account location (accoutn collector has not run yet) and then G&L wants to
update an account, that does not exists in the "old" OU so it fails.

It would not be a problem if all the change requests items would be in one
change request, but since two different change requests are created, I do not
know how to handle this.

Is there any built-in solution for this use case?

Thank you for your help.

  • Not the most elegant solution, but this might do the job.

    As there is no way to ensure that update account will be executed before move
    account, consider adding a delay node in the move account WF, so that it will
    start after the update has been completed.
    Selected as Best
  • Not the most elegant solution, but this might do the job.

    As there is no way to ensure that update account will be executed before move
    account, consider adding a delay node in the move account WF, so that it will
    start after the update has been completed.
    Selected as Best