In some Reviews, you may notice that an action was performed and an Entitlement was revoked even though the Review is in the Completed state. You may also see a related comment in the comments history for the affected review items.
When you open the Review items where the decision was changed, you will see that the change occurred on a date after the Review was marked as Completed.
This is not an action performed by the user, but rather an event that is triggered when one or more Entitlements are set to Maintain with Expiration. When the maintenance period reaches its expiry date, the event is triggered, and the Entitlements are revoked. This occurs even if the Review is already in the Completed state. As a result, the following system-generated comment is generated:
Revoke on expiration of maintain state.Related Articles
RSA Governance & Lifecycle - Securience Access Anywhere - Implementation Blueprint 17Number of Views Account Access and Ownership Review result progress bar does not show 100% though all items are completed in RSA Via Lifec… 82Number of Views Account summary table export includes the HTML tags that construct the account mapping button in RSA Identity Governance &… 42Number of Views Review overall status bar is not updated when a review is completed in RSA Identity Governance & Lifecycle 123Number of Views RSA Identity Governance & Lifecycle change request of type Delete Account shows as status Completed, but the Account Chang… 249Number of Views
Trending Articles
RSA Authentication Manager 8.9 Patches and Hotfixes Readme RSA MFA Agent 2.5 for Microsoft Windows Installation and Administration Guide RSA-2026-24: RSA Authentication Manager Security Update for Third-Party Component Vulnerabilities IDR SSO - Step 3: Deploy the Identity Router RSA Authentication Manager 8.9 Setup and Configuration Guide